| Home Page: Okeefe Family Website |
Construction of the New Sunset Beach, NC, Bridge
Jo O'Keefe Copyright 2010 All Rights Reserved
Projected completion date: December 14, 2010
English Construction Company, Inc., Lynchburg, Virginia
Page 1
![]() |
|
|
Sketch of the
new bridge to Sunset Beach, NC
|
|
![]() |
|
|
My introduction
to the bridge to be began when several of these signs piqued my curiosity.
They were protecting the lilies described below.
|
|
![]() |
![]() |
|
Spring 2007:
A total of 1,166 bulbs of the Rain
Lily, Zephyranthes simpsonii, a threatened species, were moved
from the right of way across from Bill's Seafood, to the Brunswick County
Cooperative Extension Agency. They will continue to grow there until
the bridge is completed. Then they will be replanted near the mainland
base of the new bridge. Melissa
Miller, NCDOT Environmental Biologist, supervised the relocation. Photos
were taken by Environmental Biologist Melissa Miller.
|
|
|
February 19,
2008: English Construction staff, along with NCDOT engineers, arrived
on the site. Soon afterwards they began to clear trees and do other
preliminary tasks.
|
|
![]() |
![]() |
|
March
31, 2008: On a drizzly day, English Construction Company began to
lower the first pile.
|
Lowering
the first pile with a generator-powered hammer while a second crane
picks up the next pile
|
![]() |
![]() |
|
Near
the end of lowering the first pile with the second pile ready
|
Checking
placement to ensure that the pile is level
|
![]() |
![]() |
|
Moving second
pile into place; first pile is to its left
|
Attaching
hammer to second pile - last photo from 3/31/08
|
![]() |
![]() |
|
April 25, 2008:
Since I posted photos of the first and second enormous piles being hammered
into the ground, more have been inserted. Green re-enforcing steel known
as rebars was placed along side each pile. A large concrete footing
was poured to hold the piles and rebars in place. Four footings have
been constructed. This photo shows two footings. One bridge support
column will be erected around each circle of rebars on each footing.
There will be more than 40.
|
Workmen are welding
behind an idle crane.
|
![]() |
![]() |
|
April 30, 2008:
Once again my white balance was off. Sorry. This shows one of several
cement mixers pouring concrete into a bucket. The concrete was to make
two more footings around rebars.
|
The bucket being
lifted by a crane -- photo from a different camera.
|
![]() |
![]() |
|
Bucket
being lowered over frame of footing
|
Bucket
being pushed into place
|
![]() |
![]() |
|
Forms
that will go around rebars inside columns
|
Near
the dust, pounding and enormous construction vehicles, several Live
Oaks remain, this one enshrouding -- as always -- the old Sunset Beach
Bridge.
|